In Both Towns - Drop crews are working to complete installing fiber to residences. Fiber connections are being spliced and tested.
Red Oak – Construction plowing will move to Ironwood. Installations are continuing now as we get fiber splicing test results. The Bluegrass Road area is on hold as we continue to wait on the city and railroad.
Clarinda – Minor construction issues are being finalized. We should be starting installations to customers soon as we get verified fiber test results.